GF Projects 2024
Completed / Scheduled
4BHL |
Sump |
2,098 |
02/15/24 |
2ETW |
Emgy Rot Repair |
10,100 |
03/06/24 |
1ETW |
Electrical (dehumid) |
968 |
03/25/24 |
16ETW |
Stair repair |
493 |
03/27/24 |
1ETW |
Sister posts |
0 |
04/06/24 |
3BHL |
Repair Deck |
4,700 |
04/11/24 |
13BHL |
Sump & waterguard |
7,990 |
06/05/24 |
|
Subtotal |
26,349 |
|
To Be Determined
6ETW |
Replace bulkhead |
17,255 |
1ETW |
Sump |
3,570 |
3ETW |
Sump & dehumid |
11,619 |
8BHL |
Seal DW pipe & WGrd |
7,391 |
5ETW |
mv sump & smartjax |
13,349 |
2ETW |
Dehumidifier |
2,030 |
2BHL |
Sump & dehumid |
4,984 |
BldC |
Paint & repair |
32,000 |
Garage |
Replace roof |
8,000 |
1,9,11ETW |
Structural |
70,000 |
|
Subtotal |
170,198 |
|
Total (Comp + TBD) |
196,547 |
Previous post
Building Repair Budget
As of March 31 24 Budget Spent YTD Remaining BUILDING MAINTENANCE & REPAIR 5725 Stairwell Maintenance 6,000 6,000 5730 Entrance Steps /