GF Projects 2024

Completed / Scheduled

Unit Description Cost Date
4BHL Sump 2,098 02/15/24
2ETW Emgy Rot Repair 10,100 03/06/24
1ETW Electrical (dehumid) 968 03/25/24
16ETW Stair repair 493 03/27/24
1ETW Sister posts 0 04/06/24
3BHL Repair Deck 4,700 04/11/24
13BHL Sump & waterguard 7,990 06/05/24
Subtotal 26,349

To Be Determined

Unit Description Cost
6ETW Replace bulkhead 17,255
1ETW Sump 3,570
3ETW Sump & dehumid 11,619
8BHL Seal DW pipe & WGrd 7,391
5ETW mv sump & smartjax 13,349
2ETW Dehumidifier 2,030
2BHL Sump & dehumid 4,984
BldC Paint & repair 32,000
Garage Replace roof 8,000
1,9,11ETW Structural 70,000
Subtotal 170,198
Total (Comp + TBD) 196,547